Alerts and Notices

 

Traffic Alerts

 
Traffic Alert: Construction Activities for Week Ending November 7, 2014
10/31/2014

Traffic Alerts The following is a Traffic Alert Issued by the Town of Framingham Department of Public Works for week ending November 7, 2014.

Central Street Bridge Deck Repairs at Edgell Road

Contractors will finish paving and striping on the bridge. Two way traffic will be maintained.

Concord Street Conduit and Sidewalks

Beginning at Route 9 and traveling south on Concord Street towards Hartford Street, contractors will be forming and pouring concrete sidewalks. Moderate traffic and pedestrian impact during construction.

Concord Street Roadway Improvements (Downtown)

The contractor is anticipated to continue sidewalk sawcutting and excavation for conduit trenches. Moderate traffic and pedestrian impact during construction.

Irving Street, Herbert Street and Loring Drive Water and Sewer Improvement Project

Contractors continue the installation of new water facilities. Expect delays.

John J. Gallagher Drive Road and Sidewalk Restoration

The Framingham Department of Public Works will be installing curbs and sidewalks. Moderate pedestrian and traffic impact is expected.

Logan Express

The Massachusetts Port Authority’s contractor, Consigli Construction, is anticipating the delivery of large scale precast pieces for the new Logan Express Parking Garage in Framingham beginning the week of October 6th through mid to late November. The deliveries are anticipated to take place prior to rush hour, however; there is a potential for delays along Route 9 eastbound.

Route 9 Bridge near Country Club Lane

The MassDOT contractor will continue work involving various utilities relocating utility poles and wires on the north side of Route 9, this work should not require lane closures. Reduce speed while traveling through the construction work zone and use caution in the area.

Saxonville-Concord Street

In the area of 'A' Street and School Street the contractor will continue to perform curbing, sidewalk, mast arm foundation installation, and utility transfer work. Occasional moderate traffic delays are anticipated while utility work is underway. Traffic will be managed utilizing a one lane alternating traffic pattern through the work zone. Expect delays.

Waverly Street and Winthrop Street Intersection Sewer Realignment

The contractor will be working on sewers and manholes between 759-763 Waverly Street and at Nevins Way. Minimal traffic impact.

Water Street at Central Street

The contractor will be installing temporary traffic controls and preparing the work area for demolition of the existing retaining wall. Minor traffic impact due to shifted and reduced lanes. Use caution when traveling in the area.

Winter Street Bridge over CSX

NSTAR and other utility relocations will continue in the vicinity of the bridge. This work is anticipated to have minimal impact on traffic in the area.

Police detail officers will be on site to assist in the facilitation of traffic flow and to assist with emergency response. Construction activities are scheduled to take place daily (Monday through Friday) between the hours of 7:00 a.m. and 4:00 p.m. unless otherwise noted. Thank you.

Follow us on FACEBOOK and Twitter.



Construction Alerts and Notices



eNewsletter

Department of Public Works eNewsletter - August 2013

Department of Public Works eNewsletter - July 2013

Department of Public Works eNewsletter - June 2013

Notices

Sand Barrell Locations

Arterial Roadways List

Maps

Salem End Road Paving Map



Sign up to receive construction alerts and other project information by email.